Bypass road of Sfântu Gheorghe City
The new bypass will help to relieve traffic congestion in the town of Sf. Gheorghe and will see improved connections to nearby localities
It will also help to reduce the time spent on travel and the CO2 emissions.
The implementation of the project will lead to the construction of:
- 4 roundabouts,
- 3 passages over the railway (2 passages with a length of 355m each and one of 526m),
- 2 service areas (with in each of them 25 parking spaces for cars, 16 parking spaces for heavy vehicles and public toilets),
- a maintenance center (at the intersection of DN13E and VOSFG) at km 7+950.
Our mission(s)
- Feasibility study
- Elaboration of the project for authorization of the execution of works
- Building authorization